Cabonne Council is currently delivering a range of exciting infrastructure and community projects across the region. These initiatives aim to enhance local facilities, support economic development, and improve the quality of life for residents and visitors alike. Below is an overview of the key projects underway.

Major Projects

Peak Hill Rd Upgrade (ROSI)
Cabonne Council is undertaking an upgrade of Peak Hill Road, a project funded under the Roads of Strategic Importance (ROSI) initiative. The upgrade will cover the full 16 kilometers of Peak Hill Road within the Cabonne Council area. The project is part of the council's ongoing recovery efforts after floods, with the aim of improving infrastructure and enhancing safety.

February 2026 Update -  Topsoil stripping has now been completed on the first stage of works, covering the final 3 kilometres of the project to the Parkes Shire boundary. Initial subgrade and base preparation is underway. The first base slab for the new culverts on the realignment section has been poured, and formwork for the second culvert is currently in progress.

 

Potable Water Project - Yeoval and Cumnock

Cabonne Council contractors have completed installing dual check valves at every property in Cumnock and Yeoval as part of the potable water upgrade. An update on the next steps will be provided shortly. 

 

 

 

 

 

 

 

Community Projects

YEOVAL

Yeoval Recreation Ground

New play equipment has now been installed, giving families and young users an early glimpse of the revitalised space. Electrical infrastructure has also been completed at the scoreboard site, preparing the precinct for its next major addition.

Upcoming works include installing the new scoreboard and fitting the remaining park furniture as the project heads into its final stages.

 

EUGOWRA 

Eugowra Sportsground Lighting

Work has commenced on the restoration of lighting at the Eugowra Sportsground, with the project on schedule for completion in April 2026. The contractor is establishing the site this week (wc 9 February 2026), ahead of trenching works set to begin next week. To allow this stage to proceed safely, the sportsground will be temporarily closed.

Next steps include completing a power upgrade while the project team awaits delivery of the new lighting infrastructure.

 

Refurbishment of Former Eugowra Pre-School Site

Refurbishment works at the former Eugowra Preschool site are progressing well, with the project on track for completion in April 2026. Most internal works are now finished, with contractors currently addressing minor defects. A variation has also been submitted to the funding body seeking approval to complete landscaping and fencing around the building, expanding the project’s final scope.

Upcoming tasks include fitting out the kiosk, installing roof gutters, and finishing the landscaping.

 

Restoration of Memorial Park, Eugowra

Restoration of Memorial Park in Eugowra is moving forward, with the project scheduled for completion in July 2026.

A Request for Tender for the park’s landscaping works was released on 28 January, with the outcome set to be reported to the March Council meeting.

Next steps include seeking quotes for new playground equipment and an upgraded amenities block as planning for the revitalisation continues.

 

Restoration of Eugowra Historical Museum & Bushranger Centre 

The original scope of works has now been fully completed. A variation has been submitted to the funding body seeking approval to add a new storage shed behind the museum, which would enhance the centre’s capacity to protect and manage its collection.

Next steps include lodging a Development Application for the shed once approval for the project variation is received.

 

Activation of Eugowra CBD

Planning for the activation of the Eugowra CBD is continuing, with the project scheduled for completion in August 2026.

Council is currently awaiting a second quote for the civil design, the next key step before detailed planning can begin. Once received, a contractor will be engaged, with design work expected to start early in the new year.

Due to several major projects nearing completion elsewhere in the shire, the CBD activation has not been the primary focus in recent months. Council expects to dedicate more resources to the project from April.

 

Eugowra Showground Power Activation

Progress is underway on the Eugowra Showground activation project, with completion scheduled for April 2026.

Essential Energy approvals have now been secured, clearing the way for construction to begin. The contractor has commenced work on site, marking a key milestone for the project.

The showground will be closed next week as trenching and other groundwork gets underway.

 

Restoration of Eugowra Pool & Amenities

The Eugowra Pool refurbishment is the first CAP24 project completed, officially opening on 22 November. Works included full amenities upgrade to current standards with disability access, resurfacing of pools, new shade structures, plant room shed, landscaping, and a rainwater tank.

 

 

MOLONG

Molong Hockey Field Relocation

Work on the new synthetic hockey facility remains on track for completion in April 2026, with several major components now finished.

The synthetic turf has been installed and sand-filled, and is awaiting certification from Hockey NSW. Fencing around the field is complete, and electrical contractors have begun installing pits and conduits.

Next steps include completing the car park, securing approval to proceed with the revised dugout and amenities design, and installing field lighting.

 

Activation of Hunter Caldwell Sports Precinct

Upgrades at the Hunter Caldwell fields continue to progress toward the April 2026 completion target.

A new pump and water licence now allow irrigation from Molong Creek, and one of two travelling irrigators has arrived, with the second due this week. The eastern irrigation system has been connected to the new pump, ensuring both fields are now irrigated. Work to replace the old copper log fence with a post‑and‑rail fence begins the week of 2 February.

Next steps include turf laying in late February or early March, weather permitting, and installing a power bollard near the canteen.

 

Molong Showground Upgrade

This progress is on hold until the wastewater load from the existing and planned new amenities is confirmed. 

Street Pots along Bank Street, Molong
Several of the large grey pots along Bank Street, Molong have recently begun to show signs of cracking. An investigation has identified a manufacturing defect affecting all of the original units. The manufacturer has agreed to replace the entire batch. Replacement pots will be stored and installed as required should any additional units begin to fail.

Pillans Park Upgrade

Cabonne Council has completed the Pillans Park upgrade. Final tidy up has commenced, the park is now open to the community. 

 

 

 

MANILDRA

Manildra Multipurpose Courts Relocation

The relocation of the Manildra multipurpose courts is progressing well, with the project on track for completion in April 2026.

Asphalt surfacing has now been completed, and fencing works are finished except for the installation of the large gates. A request for quote has also been issued for the concrete footpath that will link the new courts to the Golf Club house.

Upcoming works include rectifying minor asphalt defects, painting and line marking the courts, commencing lighting installation in February, and constructing the connecting footpath.

 

 

CANOWINDRA

Construction of a cabin at the Canowindra Caravan Park

Construction of the new cabin at the Canowindra Caravan Park is moving forward, with final preparations underway ahead of installation.

The cabin underwent inspection in the final week of January, with a small number of kitchen‑related defects identified. These are now being rectified by the supplier. A quote has also been requested from Central Tablelands Water to install the required fire hydrants—an essential step before the cabin can be delivered and placed on site.

Next steps include installing the fire hydrants, preparing the site with footings and associated groundwork, and finally delivering the cabin and connecting it to services.

 

Canowindra CHS & Library Refurbishment

The refurbishment project is nearing completion after construction began in May following an extensive design, approval, and tendering process. Despite some challenges during demolition, works have progressed smoothly, and final painting, fit-off, and touch-ups are underway. Practical completion is expected by the end of 2025.

Next Steps:

  • Furniture delivery and Meals on Wheels freezer installation in January
  • Library and office move-in, followed by public opening in February 2026

The project will deliver a larger, more functional library space, new public toilets, upgraded and accessible council offices, and a new community meeting room.

 

Cabonne Pools

Upgrade seven pool amenities across communities within Cabonne

  • Plantroom, Electrical and Filter Upgrades (All pools)
  • Wet deck as part of the plantroom upgrades (Cumnock, Yeoval)
  • Hot water systems (Cudal, Cumnock, Manildra, Yeoval)
  • Perimeter fencing and Landscaping (Canowindra, Cudal, Molong, Cumnock, Yeoval)
  • Accessible carparking (as per available contingency funding
  • Consultant costs – Plantroom upgrades
  • SCADA Software program for plantrooms

 

 

 

 

 

 

Roads/Transport

Kent Road Closure - 24 March 2026 - Causeway Improvements

Please be advised that Kent Road, between Burrendong Way and Dalton Road will be closed from Tuesday, 24 March 2026 to allow contractors to begin improvement works on the causeway. The works are expected to take two weeks given favourable weather. Working hours will be between 7am and 5pm, weekdays.

Detour Route:
Traffic will be diverted from Burrendong Way → Fanning Road → Dalton Road → Kent Road, with the same route operating in reverse.

Local Access:
Local traffic will still be able to access properties:
• From the Burrendong Way end, up to just before the work site
• From the Dalton Road end, just past the work site

To keep updated visit Live Traffic NSW
For more council project updates visit https://www.cabonne.nsw.gov.au/Council/Projects

 

 

Boree Street, Manildra Road Closure - Thursday, 12 March - Sunday, 15 March 2026

Please be advised that Boree Street, Manildra will be closed from 9am on Thursday, 12 March through to Sunday, 15 March 2026.

 

UGL will be carrying out works in the area during this time.

 

Detour Information:
Traffic will be diverted via Kiewa Street → Dederang Street, crossing just over the western end of the rail line, then returning to Boree Street / Yellow Box Road.

 

The same detour will operate in reverse.
We appreciate your patience and ask all road users to follow signage and drive with care.

 

Lower Lewis Ponds Rd Closure - Tuesday, 27 January 2026

Lower Lewis Ponds Road, between Ponds Lane and Ophir Reserve, will be closed from 27 January for approximately six weeks while upgrades to the causeway are completed. There will be no access to Ophir Reserve from the south side of Lower Lewis Ponds Rd during this time. Access from the north side of the reserve will still be available.
Keep updated with Live Traffic NSW

 

Major Road Patching Works Scheduled Across Key Routes in Late 2025 and Early 2026

Council will be undertaking a series of heavy patching works across several major roads starting late November 2025, with sealing and finalisation planned before Christmas and resuming in early January 2026, weather permitting.

Scheduled Works:


MR 310 Cudal to Canowindra Road

  • Start Date: 16 February 2026
    • Duration: Approx. 26 days, weather permitting

Motorists are advised to expect lane closures, traffic control, and possible delays during these periods. Council appreciates the community’s patience and cooperation as these essential road improvements are carried out.