Peak Hill Rd Upgrade (ROSI)
Cabonne Council is undertaking an upgrade of Peak Hill Road, a project funded under the Roads of Strategic Importance (ROSI) initiative. The upgrade will cover the full 16 kilometers of Peak Hill Road within the Cabonne Council area. The project is part of the council's ongoing recovery efforts after floods, with the aim of improving infrastructure and enhancing safety.
February 2026 Update - Topsoil stripping has now been completed on the first stage of works, covering the final 3 kilometres of the project to the Parkes Shire boundary. Initial subgrade and base preparation is underway. The first base slab for the new culverts on the realignment section has been poured, and formwork for the second culvert is currently in progress.
Potable Water Project - Yeoval and Cumnock
Key milestones include ongoing water quality monitoring since 2021, the full disinfection of the Molong–Cumnock–Yeoval water main and reservoirs in 2022, and the commencement of routine fortnightly microbiological sampling in July 2025. All physical, chemical and microbiological test results since 2021 meet the Australian Drinking Water Guidelines.
Additional infrastructure has been installed at both reservoirs to allow for extra chlorine dosing if required, and Dual Check Valves (DCVs) were installed at local properties in Cumnock and Yeoval in February 2026. These valves prevent water from private systems, such as rainwater tanks, from flowing back into Council’s network.
While significant progress has been made, the Cumnock and Yeoval water supplies have not yet been officially declared potable. Council will issue a formal announcement once all final approvals are complete.
Council has now completed all reports and documentation required by NSW Health and Department of Climate Change, Energy, the Environmental and Water (DCCEEW) to support potable water status for Cumnock and Yeoval.
Eugowra STP Mid-Scale Solar Project
Council’s 2.14MW solar plant with 5.5MWh battery storage at the Eugowra Sewerage Treatment Plant is close to completion, with construction finishing in early April. Covering around 1.5 hectares, the system will export electricity to the grid, helping offset Council’s overall power use and emissions. Essential Energy network upgrades will begin soon, with energisation scheduled for 1 July 2026. After connection, the plant will undergo six weeks of testing before operating at full capacity.