Projects

Cabonne Council is currently delivering a range of exciting infrastructure and community projects across the region. These initiatives aim to enhance local facilities, support economic development, and improve the quality of life for residents and visitors alike. Below is an overview of the key projects underway.

Major Projects

Peak Hill Rd Upgrade (ROSI)
Cabonne Council is undertaking an upgrade of Peak Hill Road, a project funded under the Roads of Strategic Importance (ROSI) initiative. The upgrade will cover the full 16 kilometers of Peak Hill Road within the Cabonne Council area. The project is part of the council's ongoing recovery efforts after floods, with the aim of improving infrastructure and enhancing safety.

September 2025 Update - Initial tree and vegetation clearing has now been completed as part of the Peak Hill Road upgrade. Vegetation works were required along the full length of the project, with the first 10km now finished. The remaining vegetation works will be subject to a new tender, which will be advertised in the coming weeks. Additionally, tenders for the road construction and culvert works are also being readvertised and close at 12pm, Wednesday, 24 September. View here

October 2025 Update - New tenders have been received for the construction of the 16km of Peak Hill Road. These tenders are currently being assessed.

November 2025 Update - Council has been advised that our tree and vegetation contractor will begin Stage 2 Tree and Vegetation works on Peak Hill Road from Wednesday, 19 November 2025.

These works are expected to take approximately four weeks. During this time, traffic control will be in place, with one-lane traffic operating through the work zone.

This activity is an important step in preparing the site for upcoming civil construction works as part of the Peak Hill Road upgrade.

 

Potable Water Project - Yeoval and Cumnock

Cabonne Council contractors have begun installing dual check valves at every property in Cumnock and Yeoval as part of the potable water upgrade.

Licensed plumbers are carrying out the work, and residents will be notified at least 24 hours before work begins at their property.

The installation, funded by Council, helps prevent potentially contaminated water from flowing back into the mains.

Water supply may be interrupted for up to two hours, and some temporary discoloration may occur.

The project is scheduled for completion by the end of 2025.

 

 

 

 

 

 

 

Community Projects

YEOVAL

Yeoval Recreation Ground

The tennis courts, tennis shed, footpaths, and concrete apron were completed last financial year. Community consultation has been undertaken for the upgrade to play equipment and installation of a new electronic scoreboard.
Next steps: Install the scoreboard and play equipment before the end of the year.

 

 

 

EUGOWRA 

Eugowra Sportsground Lighting

Work is progressing on the Eugowra Sportsground lighting restoration. A contractor has been engaged, and a startup meeting was held on 10 November. Procurement of non-upgrade equipment has commenced, pending Essential Energy approval. Completion is scheduled for April 2026.

 

Refurbishment of Former Eugowra Pre-School Site

The former ECCC building has been rebuilt with flood-resilient materials and will provide changerooms, a multipurpose hall, office, referees’ facilities, and kiosk. Accessibility and fire compliance upgrades have been completed. The project is anticipated to finish by mid-January, with a proposed Stage 2 to restore the playground pending grant variation approval.

 

Restoration of Memorial Park, Eugowra

The final concept design has been received. Quotes for the toilet block and tenders for playground equipment and landscaping will be reported to the March Council Meeting. Completion is expected by July 2026.

 

Restoration of Eugowra Historical Museum & Bushranger Centre

The museum refurbishment reached practical completion on 2 December, with the committee now moving exhibits back in. The upgrade includes a new reception and family history room, flood-resilient finishes, improved accessibility, and compliance with fire codes. Additional works such as façade repairs, new lighting, and internet have also been completed. Next steps include a proposed new machinery display shed, with a development application planned for early 2026. Project completion is set for December 2025.

 

Activation of Eugowra CBD

Community consultation has been completed, and a Request for Quote for civil design works was issued on 7 November. Next steps include engaging a contractor and commencing design early in the new year, with planning expected to finish by March 2026. Overall completion is scheduled for August 2026.

 

Eugowra Showground Power Activation

A contractor has been engaged, and a startup meeting with stakeholders was held on 10 November. Procurement of non-upgrade equipment has commenced, pending Essential Energy approval. Completion is expected by April 2026.

 

Restoration of Eugowra Pool & Amenities

The Eugowra Pool refurbishment is the first CAP24 project completed, officially opening on 22 November. Works included full amenities upgrade to current standards with disability access, resurfacing of pools, new shade structures, plant room shed, landscaping, and a rainwater tank.

 

 

MOLONG

Molong Hockey Field Relocation

Key structural and surface preparation works have been completed, including kerb installation, final trimming of the base pavement layer, asphalt preparation, fence post installation, and footpath preparation.

Next Steps:

  • Asphalt works scheduled to commence on 15 December 2025
  • Concrete pouring for footpaths following asphalt completion
  • Installation of fencing panels after surfacing works

The project remains on schedule, with upcoming tasks focused on surfacing and finishing elements to meet timelines.

 

Activation of Hunter Caldwell Sports Precinct

Earthworks have been completed, with the existing road base material removed, stockpiled, and repurposed for future council projects. A 300mm layer of topsoil has been installed and levelled in preparation for turfing. Irrigation works began in early December using an existing water license from the creek. Turf installation has been postponed until early in the new year to allow for the setup of new travelling irrigators.

Fencing at the Betts Street site has been completed, including lowering the existing fence and reinstating gates. Steel fencing at the soccer fields, replacing treated pine logs, has been delayed until February 2026 due to contractor availability.

Next Steps:

  • Turfing scheduled for late January/early February
  • Steel post and rail fencing installation at soccer fields in early 2026

The project is progressing steadily, with groundwork and irrigation completed ahead of final surfacing and fencing works.

Molong Showground Upgrade

This progress is on hold until the wastewater load from the existing and planned new amenities is confirmed. 

 

MANILDRA

Manildra Multipurpose Courts Relocation

Asphalt surfacing has been completed and is curing for a three-week period. All fencing installation is finished, and preparation for concrete driveways and footpaths is complete. Drainage works have also been successfully installed.

Next Steps:

  • Core drilling for tennis and netball posts
  • Pouring footpaths and driveway
  • Cleaning asphalt surface
  • Court painting and line marking
  • Lighting and water service installation scheduled for January 2026

The project remains on schedule, with courts expected to be ready for use over the Christmas period.

 

CANOWINDRA

Construction of a cabin at the Canowindra Caravan Park

The cabin is nearly complete and ready for delivery and installation. However, additional fire compliance requirements have been identified, and options for installing a hydrant are being assessed.
Next Steps: Install the cabin and seek quotes for hydrant installation.

 

Canowindra CHS & Library Refurbishment

The refurbishment project is nearing completion after construction began in May following an extensive design, approval, and tendering process. Despite some challenges during demolition, works have progressed smoothly, and final painting, fit-off, and touch-ups are underway. Practical completion is expected by the end of 2025.

Next Steps:

  • Furniture delivery and Meals on Wheels freezer installation in January
  • Library and office move-in, followed by public opening in February 2026

The project will deliver a larger, more functional library space, new public toilets, upgraded and accessible council offices, and a new community meeting room.

 

Cabonne Pools

Upgrade seven pool amenities across communities within Cabonne

  • Plantroom, Electrical and Filter Upgrades (All pools)
  • Wet deck as part of the plantroom upgrades (Cumnock, Yeoval)
  • Hot water systems (Cudal, Cumnock, Manildra, Yeoval)
  • Perimeter fencing and Landscaping (Canowindra, Cudal, Molong, Cumnock, Yeoval)
  • Accessible carparking (as per available contingency funding
  • Consultant costs – Plantroom upgrades
  • SCADA Software program for plantrooms

 

 

 

 

 

 

Roads/Transport

Heavy Patching Works

Heavy patching works will take place on MR61A near Heifer Station Wines starting 6 January 2026.  Please allow extra time when travelling through the area and follow all traffic management directions.

 

Road Closure Notice – Baghdad Road, Cargo

Baghdad Road, after the 'Cargo Common grid' will be closed on Monday 15 and Tuesday 16 between 8am and 3pm for culvert upgrade works. 

 

Road Works Underway Across Key Local Routes

Council crews have commenced road improvement works on Gumble Road, with activity currently focused around the Hall area. These works form part of a broader sealing and resealing program scheduled throughout December.

The planned works include:

  • 12 December – Patching on Bowen Park Road
  • 15 December – Sealing on Nangar Road near Sugarloaf Lane, along with patching on Gumble Road
  • 16 December – Resealing on Gumble Road, covering approximately 2.6 kilometres from the Norah Creek intersection through to the concrete culvert towards Manildra

Motorists are advised to exercise caution when travelling through these areas and to observe all traffic signage. These improvements are aimed at enhancing road safety and driving conditions for the community.

 

Bridge Repair Works - Coates Creek Bridge - 17 November 2025

Works have commenced on Coates Creek Bridge, located on Coates Creek Road. The project includes repairs to the bridge abutments, scour protection, and slope restoration.

Repairs are being carried out under the bridge, so traffic disruption will be minimal. However, please be aware there will be an increase in heavy vehicle traffic along Coates Creek Road due to the transportation of a large volume of revetment rock.

The works are expected to continue for approximately five weeks.

 

Major Road Patching Works Scheduled Across Key Routes in Late 2025 and Early 2026

Council will be undertaking a series of heavy patching works across several major roads starting late November 2025, with sealing and finalisation planned before Christmas and resuming in early January 2026, weather permitting.

Scheduled Works:

  • MR 61A Escort Way & MR 61B Henry Parkes Way 

    • Start Date: Week of 24 November 2025
    • Duration: Approx. 20 days, weather permitting
    • Sealing: Planned for the week of 8 December 2025
    • Break: Works will pause over Christmas and resume around 5 January 2025
  • MR 359 Peabody Road

    • Start Date: 12 January 2026
    • Duration: Approx. 5 days, weather permitting
  • MR 377 Escort Way

    • Start Date: 19 January 2026
    • Duration: Approx. 15 days, weather permitting
  • MR 310 Cudal to Canowindra Road

    • Start Date: 16 February 2026
    • Duration: Approx. 26 days, weather permitting

Motorists are advised to expect lane closures, traffic control, and possible delays during these periods. Council appreciates the community’s patience and cooperation as these essential road improvements are carried out.

 

Banjo Paterson Way, 1km north of Cumnock - 13 October 

Reconstruction north of Cumnock is progressing, and pavement rehabilitation have now been completed, with line marking to follow. 

 

Spring Hill Road Upgrade, from Cowriga Road to Blayney LGA Boundary

Culvert installation, drainage improvements, and pavement rehabilitation have been completed, with line marking to follow. 

 

Roadworks Starting on Vittoria Road – Monday 27 October - subject to weather

Heavy patching is ongoing with completion expected mid-December.