Molong Town Centre Activation Plan Update - April 2024

Published on 30 April 2024

4 photos added (2).jpg
The Molong Town Centre Activation Project is on track for completion by early June. Weather permitting, it is expected this could be earlier. 

The concrete wall has been poured and the StrataVault has been installed. Crews are currently applying the topsoil which is expected to be completed by the end of Wednesday, 1 May which will then allow them to undertake the first pour for the concrete roof. 

Weather permitting, the pavers are booked in to be laid next week (week commencing 6 May). 

Council would like to thank the community for their patience while this work is being undertaken and remind residents and visitors to continue to support the local businesses during the project. 